The Boring PartsFederalLocal · USLocal · Canada
Steele County, North Dakota

Steele County public meetings in 2025

7 substantive meetings from 2025, with official agendas or minutes and plain-English summaries.

Tue Dec 2, 2025

Meeting

Steele County Water District to review drainage, dam, and joint board meetings

The Steele County Water Resource District is holding its regular monthly meeting to discuss updates on drainage projects, a complaint, and upcoming joint water board meetings. The board will also consider office updates, a reimbursement policy, and financial reports.

water-resourcesdrainagedammeetingnorth-dakota
Tue Nov 4, 2025

Meeting

Board approves $2.1M flood mitigation plan and bid process for Drain 1 Outlet

The Steele County Water Resource District approved a construction plan for the Drain 1 Outlet flood mitigation project, selecting a modified rock chute design over a drain extension. The board authorized the advertisement of construction bids, which will be opened on December 15, 2025. Additionally, the board approved a drain tile permit and authorized the purchase of right-of-way land for the project.

flood-controlwater-resourcesconstructionzoningbudget
Tue Oct 7, 2025

Meeting

Steele County Water Resource District to review FEMA projects and drain work

The Steele County Water Resource District is holding its regular monthly meeting to discuss and decide on drainage-related matters, including FEMA projects, drain cleanouts, culvert installations, and assessments. The board will also consider new drain tile installations under 80 acres for four landowners and review a drainage complaint reimbursement policy. The meeting includes public comment and reports on joint water resource district meetings.

drainagewater-resource-districtfemainfrastructurepublic-hearingassessments
Mon Sep 15, 2025

Meeting

Steele County Drain 1 project ballot vote ends Oct 15

The Steele County Water Resource Board met to review the Drain 1 project history, schedule, and maps. A landowner raised a question about the benefit percentage, which will be reviewed after the vote if it passes. The ballot vote ends October 15, 2025, at noon. The next general monthly meeting is scheduled for October 7, 2025.

water-resource-districtdrainageballotassessmentmeeting-minutes
Mon Mar 3, 2025

Meeting

✓ Decided: Board orders fill of unauthorized drain on Fisher property

The Steele County Water Resource Board approved a Notice of Order requiring the fill of an unauthorized surface drain on the Fisher property (NE ¼ of Section 15) to elevation 1121, about 400 feet wide, after determining the ditch improvements exceeded normal maintenance and required a permit. The board also kept the existing Drain 12 assessment district unchanged and discussed but did not decide on the Fugleberg drainage permit, which will be revisited in April. FEMA-funded projects for Drains 6 and 11 are complete, while Drain 1 mitigation awaits FEMA obligation.

Tue Feb 4, 2025

Meeting

✓ Decided: Drainage complaint finds Fisher property violated permit rules

The board reviewed a drainage complaint and found that surface ditch improvements on the Fisher property exceeded normal maintenance and required a permit, but deferred action on other properties pending further investigation. The Drain 4 & 12 re-assessment was tabled, and the board discussed FEMA-funded projects and the Elm River Dam construction status.

Thu Jan 9, 2025

Meeting

Steele County Water Board to review FEMA sites, drainage complaints, dam meeting

The Steele County Water Resource District will hold its regular meeting to discuss updates on FEMA-related drainage projects, a drainage complaint, and re-assessments of several drains. They will also address the Elm River Dam meeting, joint water resource district matters, and routine administrative items like contracts and the treasurer's report.

water-resourcesdrainagefemadamcontractsmeeting
✓ Decided: Board directs preparation of drain reassessment documents for Drains 4, 11, 12

The Steele County Water Resource Board approved a motion to direct Engineer Pease and Attorney Tostenson to prepare documents for reassessments of Drains 4, 11, and 12. The board also approved contracts for legal and engineering services, continued board positions, and approved the treasurer's report and bills. FEMA updates were provided, including approval of mitigation for Drain 1 and completed construction for Drains 6 and 11.