Fri Sep 5, 2025

Council

Council receives final 2025 street rehabilitation project update; work wrapping up with final paving and punchlist items.

The council is receiving the final weekly update on the 2025 Street Rehabilitation Project. Crews are completing punchlist items and will pave the Public Works parking lot the week of September 8. This is the last update for the season.

streetsconstructionpublic-worksinfrastructure
Fri Aug 22, 2025

Council

Street rehabilitation project enters final paving phase

This is a weekly update on the 2025 Street Rehabilitation Project, not a council meeting agenda. It details the final paving of Oak Leaf/South Drive area and provides safety and maintenance tips for residents.

streetsconstructionpavingpublic-workssafety
Fri Aug 1, 2025

Council

Council receives weekly update on 2025 Street Rehabilitation Project in Golden Lake and Oak Leaf/South Drive areas

This is a weekly project update, not a council decision meeting. The agenda reports that crews are restoring streets, replacing curbs and driveways, and will stripe roads in the Golden Lake area; in the Oak Leaf/South Drive area, base course paving is scheduled for late July and final pavement in mid-August. Residents are advised to follow traffic signs, drive slowly, and water new sod for 30 days.

streetsconstructionpublic-worksinfrastructureproject-update
Thu Jul 10, 2025

Council

Street rehabilitation project continues with milling, seal coat, and paving

The council is receiving a weekly update on the 2025 Street Rehabilitation Project. Work includes milling, seal coating, and paving in the Golden Lake area, and storm sewer work and road reclaiming in the Oak Leaf/South Drive area. The schedule is tentative and weather-dependent.

streetsconstructioninfrastructurepublic-works
Fri Jun 27, 2025

Council

Street rehabilitation project update with Golden Oak closure

The Council is receiving a weekly update on the 2025 Street Rehabilitation Project. Golden Oak between Cameo Lane and Civic Heights Drive will be closed for sanitary sewer installation. Work is expected to be completed by July 3rd.

streetsconstructioninfrastructuresewer
Fri May 30, 2025

Council

Street rehabilitation project continues with milling and paving in June

This is a project update, not a council decision agenda. The Village Area will have street milling on June 3-4 and paving on June 5-6, with no-parking restrictions. Golden Lake Area work includes erosion control and sanitary service replacement at 2 Golden Lake Rd. Residents are advised to follow posted signs and avoid parking on affected streets.

roadsconstructionpublic-worksparkinginfrastructure
Fri May 9, 2025

Council

Street rehabilitation project continues with concrete work and road closure

The council is receiving a weekly update on the 2025 Street Rehabilitation Project. Work includes pouring concrete for curb, walk, and ADA ramp improvements, with sidewalk closures. A one-day closure of Village Parkway at Lake Dr intersection is planned for manhole work.

streetsconstructionadatrafficinfrastructure
Mon Apr 28, 2025

Council

Street rehabilitation project continues with curb and sidewalk work

The council is receiving a weekly update on the 2025 Street Rehabilitation Project, which includes removal and replacement of damaged curb, sidewalk, and ADA pedestrian ramps in the Village Area. The update also notes that work will continue into early May with concrete pouring, and advises residents to follow signage and drive cautiously near construction.

roadsinfrastructureconstructionada-compliancepublic-works
Fri Apr 25, 2025

Council

Street rehabilitation project updates with phased construction schedule

The council is receiving a weekly update on the 2025 Street Rehabilitation Project, which is divided into three areas: Village Area, Golden Lake Area, and Oak Leaf/South Drive Area. Construction is scheduled to begin April 28 in the Village Area, with other areas starting in early June. The update includes details on curb and sidewalk replacement, ADA ramp upgrades, and traffic control measures.

streetsconstructioninfrastructurepublic-worksada-compliance