Circle Pines public meetings in 2025
9 substantive meetings from 2025, with official agendas or minutes and plain-English summaries.
Council
The council is receiving the final weekly update on the 2025 Street Rehabilitation Project. Crews are completing punchlist items and will pave the Public Works parking lot the week of September 8. This is the last update for the season.
- Final layer of bituminous pavement to be laid in the Public Works parking lot (Golden Oak Dr and Civic Heights Dr area).
- Crews cleaning up all project areas and completing punchlist items.
- Residents with new sod reminded to water 2 inches per week until frost.
- Project contacts: Jeff Frahm (612-209-6961) and Emily Brown (612-849-6157).
Council
This is a weekly update on the 2025 Street Rehabilitation Project, not a council meeting agenda. It details the final paving of Oak Leaf/South Drive area and provides safety and maintenance tips for residents.
- Final layer of bituminous pavement to be paved on Oak Leaf/South Drive on August 26-27
- No parking allowed during paving work
- Street signage replacement scheduled
- Contractor responsible for sod maintenance for 30 days
- Residents advised to avoid driving through bonding agent and to water new sod
Council
This is a weekly project update, not a council decision meeting. The agenda reports that crews are restoring streets, replacing curbs and driveways, and will stripe roads in the Golden Lake area; in the Oak Leaf/South Drive area, base course paving is scheduled for late July and final pavement in mid-August. Residents are advised to follow traffic signs, drive slowly, and water new sod for 30 days.
- Golden Lake Area: crews restoring yards around curb and driveway replacements, road striping this week
- Oak Leaf/South Drive Area: grading and base course paving July 31–August 1; final pavement in mid-August
- Oak Leaf/South Drive Area: backfilling yards around curb and driveway replacements starts end of week
- Future work (Aug 4–8): finish concrete work, replace asphalt driveways impacted by project
- Contractor responsible for sod maintenance for 30 days; residents encouraged to water new sod
Council
The council is receiving a weekly update on the 2025 Street Rehabilitation Project. Work includes milling, seal coating, and paving in the Golden Lake area, and storm sewer work and road reclaiming in the Oak Leaf/South Drive area. The schedule is tentative and weather-dependent.
- Road milling scheduled for July 9-10 in Golden Lake area and Golden Lake Park parking lot
- Seal coat on W Golden Lake Rd and Woodland Rd on July 11, weather permitting
- Paving on W Golden Lake Rd and Woodland Rd tentatively starting July 12
- Storm sewer work on Golden Oak between Cameo and Oak Leaf and at South Dr/Pine Dr intersection
- Reclaiming of Cameo Ln, Oak Leaf Ln, Oak Rd, Pine Dr, and South Dr anticipated July 15-16
Council
The Council is receiving a weekly update on the 2025 Street Rehabilitation Project. Golden Oak between Cameo Lane and Civic Heights Drive will be closed for sanitary sewer installation. Work is expected to be completed by July 3rd.
- Golden Oak closed between Cameo Lane and Civic Heights Drive for sanitary sewer work
- Crews restoring yards around curb and driveway replacements in Golden Lake Area
- Storm sewer work at Golden Oak between Cameo and Oak Leaf and at South Dr/Pine Dr intersection
- Project contacts: Jeff Frahm (612-209-6961) and Emily Brown (612-849-6157)
Council
This is a project update, not a council decision agenda. The Village Area will have street milling on June 3-4 and paving on June 5-6, with no-parking restrictions. Golden Lake Area work includes erosion control and sanitary service replacement at 2 Golden Lake Rd. Residents are advised to follow posted signs and avoid parking on affected streets.
- Road milling scheduled June 3-4 in Village Area
- Road paving scheduled June 5-6 in Village Area
- No parking during milling and paving; signs and notices will be posted
- Erosion control installation along West Golden Lake Road starting June 6
- Sanitary service replacement at 2 Golden Lake Rd
Council
The council is receiving a weekly update on the 2025 Street Rehabilitation Project. Work includes pouring concrete for curb, walk, and ADA ramp improvements, with sidewalk closures. A one-day closure of Village Parkway at Lake Dr intersection is planned for manhole work.
- Crews pouring concrete for curb, walk, and ADA pedestrian ramp improvements in Village Area
- One-day closure of Village Parkway at Lake Dr intersection for manhole work
- Sidewalk closures during concrete work
- Road patching next to curb removal areas
Council
The council is receiving a weekly update on the 2025 Street Rehabilitation Project, which includes removal and replacement of damaged curb, sidewalk, and ADA pedestrian ramps in the Village Area. The update also notes that work will continue into early May with concrete pouring, and advises residents to follow signage and drive cautiously near construction.
- Removal and replacement of damaged curb and sidewalk panels in the Village Area
- Removal and replacement of pedestrian ramps at intersections to meet ADA requirements
- Concrete pouring for curb, walk, and ADA ramp improvements scheduled for May 5–9
- Potential closures of sidewalk sections during construction
- Project contacts: Construction Observer Jeff Frahm and Project Manager Emily Brown
Council
The council is receiving a weekly update on the 2025 Street Rehabilitation Project, which is divided into three areas: Village Area, Golden Lake Area, and Oak Leaf/South Drive Area. Construction is scheduled to begin April 28 in the Village Area, with other areas starting in early June. The update includes details on curb and sidewalk replacement, ADA ramp upgrades, and traffic control measures.
- Village Area (Village Parkway and Central Street) construction starts April 28, expected completion early June
- Golden Lake Area (Golden Lake Road and West Golden Lake Road) begins early June, done late July
- Oak Leaf/South Drive Area (Golden Oak Drive, Cameo Lane, Oak Leaf Lane, Oak Road, South Pine Drive, South Drive) begins early June, done mid-August
- Removal and replacement of damaged curb and sidewalk panels, including ADA-compliant pedestrian ramps
- Traffic signs and equipment arriving on site; surveyors and utility marking flags/stakes placed