The council will review several large capital expenditures including a $2.5 million loan application and various construction pay requests. Discussion includes rezoning for 402 Fifteenth Street S and multiple street maintenance projects.
- Application for $2,500,000 DW SRF Loan at 3.75% interest
- Rezoning petition for 402 Fifteenth Street S
- Pay request of $286,355.44 and change order for 10th Ave SE Bridge Replacement
- Pay request of $155,738.52 for 2025 PW Building Granular Fill Material
- Purchase of a 2026 Etnyre ECS-250 Crack Sealer
Parks, Recreation & Forestry Board
The Parks, Recreation & Forestry Board will vote on approving a memorial placement at Veterans Memorial Plaza, authorizing bids for Storybook Land improvement projects (Uncle Henry’s Outhouse Restroom and Doll House), and amending fees for ARCC Dance programs, outdoor pickleball court reservations, and Civic Arena/Theatre maintenance. They will also elect officers and review committee appointments.
- Approval of Ratzlaff Memorial at Veterans Memorial Plaza in Anderson Park
- Authorization to bid for Storybook Land Uncle Henry's Outhouse Restroom project
- Authorization to bid for Storybook Land Doll House project
- Fee amendments: ARCC Dance program fees, outdoor pickleball reservation fees, Civic Arena and Theatre maintenance fee
- Election of officers
Board of Zoning Adjustment
The Board of Zoning Adjustment will consider a request from Leao Israel to remodel four existing apartments on the second floor and add two additional apartments on the rear main floor at 122 Main St N. This requires a Special Exception and an Appeal in the C-3 Central Business District.
- Special Exception and Appeal for 122 Main St N to remodel 4 apartments and add 2 more
- Existing apartments on second floor; new apartments on rear main floor
- Property located in C-3 Central Business District
Last 30 days
Aberdeen City Council
The City Council will consider funding applications for the Water Tower and Transmission Line Project and a payment for water treatment plant roof improvements. Other business includes a rezoning request on 15th Street S and the potential dissolution of a tax increment financing district.
- Payment of $486,671.42 to Skinner Roofing for Water Treatment Plant Roof Improvements
- Rezoning petition from I-2 & C-2 to C-2 for property at 402 Fifteenth Street S
- Resolution to dissolve Tax Increment Financing District Number 8
- Public hearing set for July 6 regarding Aberdeen Water Tower Improvements Project
- Contract for architectural and engineering services for a new Aberdeen Ride Line bus barn